Astute class submarine

The Astute-class is the latest class of nuclear-powered Fleet submarines in service with the Royal Navy. The class sets a new standard for the Royal Navy in terms of weapons load, communication facilities and stealth. The boats are being constructed by BAE Systems Submarine Solutions at Barrow-in-Furness.
Seven boats will be constructed. The first of class, Astute, was launched in 2007 and commissioned in 2010, and the second, Ambush, was launched on 6 January 2011, and successfully completed its initial dive test on 30 September 2011.


History

 

Background

 

The Royal Navy has changed its submarine-employment strategy from the Cold War emphasis on anti-submarine warfare to the concept of "Maritime Contributions to Joint Operations."
Approval for studies to define the "Batch 2 Trafalgar class" (what would become the Astute class) was given in June 1991. In July 1994 risk reduction studies were authorised in parallel with the formal bid phase of the project.
On 17 March 1997, the Ministry of Defence announced that it would place a £2 billion order for three submarines and that they would be called the Astute class. On 26 March 1997 the contract was signed with GEC-Marconi for the first three boats: Astute, Ambush and Artful. These names were last given to Amphion-class submarines that entered service towards the end of World War II. GEC would build the submarines at its VSEL subsidiary (now BAE Systems Submarine Solutions).
Original plans were for seven boats of the Astute class to replace five Swiftsure-class submarines (Sovereign, Superb, Sceptre, Spartan, and Splendid) and the two oldest Trafalgar-class boats (Trafalgar and Turbulent). The Swiftsure class entered service between 1973 and 1977 and were entirely decommissioned by 2010, when only the first of the Astute class was coming into service. Trafalgar was decommissioned in December 2009, to be followed by Turbulent in 2011.
An estimated 5,900 people are employed directly as a result of the project; 3,500 BAE Systems staff at Barrow and 2,400 other people around the UK.


Batch 2

 

As of August 2006 BAE Systems was negotiating for a contract to build another four Astute-class submarines (hulls four to seven). The fourth boat was ordered on 21 May 2007, to be called Audacious, and the names of the other hulls have been agreed as Agamemnon, Anson, and Ajax. On 15 September 2011 it was announced that hull 5 would now be named Anson.
Upon the beginning of sea trials of Astute in November 2009, it was reported that long-lead items for hulls five and six have been ordered, including their nuclear reactor cores, and that the stated intention of the MoD was for a total of seven Astute-class submarines.
On 25 March 2010, BAE Systems were given the go-ahead by the government to begin construction on hulls 5 and 6, being given a £300 million contract for the "initial build" of hull five and "long lead procurement activities" for boat six.[14] In the same week the government re-affirmed their commitment to the construction of seven Astute-class submarines.
The order of seven Astute-class boats was confirmed in the Strategic Defence and Security Review of October 2010. In December that year it was confirmed by the MoD that "early work" was under way on boats five and six.
On 13 October 2011, the fifth boat "Anson", was laid down at Devonshire Dock Hall and is now under construction like boats three and four.


Construction and delays

 

BAE Systems issued a profit warning on 11 December 2002 as a result of the cost overruns and delays it was experiencing with the Astute class and also the Nimrod MRA4 maritime reconnaissance/attack aircraft. The delay was caused primarily by the problems of using 3D CAD; Armed Forces Minister Adam Ingram said in 2006 that "due to the complexity of the programme, the benefits that CAD was envisaged to provide were more difficult to realise than either MoD or the contractor had assumed." Other issues were the insufficient capabilities within GEC-Marconi which became evident after contract-award and poor programme management. BAE and the Ministry of Defence reached an agreement in February 2003 whereby they would invest £250 million and £430 million respectively to address the programme's difficulties.
A major element of this was the enlisting of advice and expertise from General Dynamics Electric Boat. The MoD also signed a design and production drawing work contract through the U.S. Navy which ran from 2004 to 2007.
Work on the second and third submarines, Ambush and Artful, proceeded well with major milestones such as the closure of Ambush's reactor compartment, demonstrating significant schedule advance compared with Astute. BAE Systems and the MoD have made efforts to reduce costs and achieved significant cost-cutting and productivity gains. A £580 million cost increase was agreed in 2007 due to maturing of the design requiring more materials, inflationary costs, and "some programme throughput assumptions at the Barrow site not being borne out."
First-of-class HMS Astute was launched by Camilla, Duchess of Cornwall on 8 June 2007.
As of March 2008 the programme was 48 per cent (or £1.2 billion) over-budget and 47 months late. Further delays due to a range of technical and programme issues brought the programme to a position of 57 months late and 53 per cent (or £1.35 billion) over-budget by November 2009, with a forecast cost of £3.9 billion for the first three Astute boats.